Brunswick Street Phase II - Storm & Sewer Separation

Dalhousie, New Brunswick

completeWastewaterSCF
Federal contribution
$262,433
Federal share30%

of $886.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2015
2016201820202022
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Dalhousie
Construction start
Sep 8, 2015(actual)
Construction end
Oct 13, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 4, 2015
  • Construction end5.8 years lateforecast Dec 31, 2016

Also in Dalhousie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46068 in the federal list. How to read these figures.