Pre and Post Treatment Upgrade at Lagoon

Dalhousie, New Brunswick

completeWastewaterCWWF
Federal contribution
$1.2M
$1,168,597
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Dalhousie
Construction start
Jul 23, 2019(actual)
Construction end
Feb 24, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2019