Pre and Post Treatment Upgrade at Lagoon
Federal contribution
$1.2M
$1,168,597
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Dalhousie
- Construction start
- Jul 23, 2019(actual)
- Construction end
- Feb 24, 2020(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2019
Also in Dalhousie
- Water Filtration Plant$2.1M
- Dalhousie Micro-Hydro Turbine$602.5K
- Brunswick Street Phase III (Victoria Street to Grey Street) - Sewer Separation and Watermain Renewal$279.2K
- Brunswick Street Phase II - Storm & Sewer Separation$262.4K
- Adelaïde Street (Brunswick to Renfrew) - Sewer Separation and Watermain Renewal$234.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47297 in the federal list. How to read these figures.