Brunswick Street Phase III (Victoria Street to Grey Street) - Sewer Separation and Watermain Renewal

Dalhousie, New Brunswick

completeWastewaterCWWF
Federal contribution
$279,211
Federal share50%

of $558.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Dalhousie
Construction start
Jul 3, 2017(actual)
Construction end
Oct 12, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2017
  • Construction end6 weeks lateforecast Aug 30, 2017