Dalhousie Micro-Hydro Turbine
Federal contribution
$602,502
Federal share60%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
20202021
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Dalhousie
- Construction start
- Oct 26, 2019(actual)
- Construction end
- Aug 16, 2021(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 3, 2019
- Construction end3 months lateforecast May 31, 2021
Also in Dalhousie
- Water Filtration Plant$2.1M
- Pre and Post Treatment Upgrade at Lagoon$1.2M
- Brunswick Street Phase III (Victoria Street to Grey Street) - Sewer Separation and Watermain Renewal$279.2K
- Brunswick Street Phase II - Storm & Sewer Separation$262.4K
- Adelaïde Street (Brunswick to Renfrew) - Sewer Separation and Watermain Renewal$234.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54728 in the federal list. How to read these figures.