203 Street Bridge Upgrade and Roundabout
Federal contribution
$1.4M
$1,395,101
Federal share33%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2015
20162017
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Langley
- Construction start
- Aug 15, 2016(actual)
- Construction end
- Jun 9, 2017(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 25, 2016
- Construction end2 months lateforecast Mar 31, 2017
Also in Langley