Norwood Water Treatment Plant
Federal contribution
$323,093
Federal share32%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2015
20162017
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Asphodel-Norwood
- Construction start
- Oct 17, 2016(actual)
- Construction end
- Jun 30, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 3, 2016
Also in Asphodel-Norwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46206 in the federal list. How to read these figures.