Rehabilitation of Norwood Town Hall
Federal contribution
$79,800
Federal share80%
of $99.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Asphodel-Norwood
- Construction start
- Jul 31, 2021(actual)
- Construction end
- Apr 2, 2022(actual)
Also in Asphodel-Norwood