Drilling of Well #4 the village of Norwood to increase capacity and reliability for our residents
Federal contribution
$51,325
Federal share45%
of $115.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2017201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Asphodel-Norwood
- Construction start
- Nov 1, 2016(actual)
- Construction end
- Mar 18, 2020(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2019