Replacement of Norwood's Treated Water Standpipe

Asphodel-Norwood, Ontario

completeDrinking WaterGIS
Federal contribution
$1.2M
$1,154,230
Federal share40%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
20232024
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 28, 2022(actual)
Construction end
Sep 19, 2024(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 1, 2024