Hyland and Briscoe Rehabilitation
Federal contribution
$913,805
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2015
20162017
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Loyalist
- Construction start
- Jul 13, 2015(actual)
- Construction end
- Dec 23, 2016(actual)
Against the original forecast
- Construction end9 months earlyforecast Sep 15, 2017
Also in Loyalist
- Construction of a Sustainable Community Hub in Loyalist Township - Retrofit$16.6M
- Detailed design and construction - Water main relining on Cambridge Crescent$302.1K
- Installation of stormwater infrastructure on Davy Street$255.7K
- Installation of stormwater infrastructure and water and sewer main replacement on Frink Avenue$175.3K
- Rehabilitation of Layer Cake Hall Public Library$173.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46214 in the federal list. How to read these figures.