Installation of stormwater infrastructure on Davy Street

Loyalist, Ontario

completeWastewaterCWWF
Federal contribution
$255,694
Federal share50%

of $511.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Loyalist
Construction start
Jun 1, 2017(actual)
Construction end
Dec 1, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end15 months earlyforecast Mar 1, 2019

Also in Loyalist

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49133 in the federal list. How to read these figures.