Installation of stormwater infrastructure and water and sewer main replacement on Frink Avenue

Loyalist, Ontario

completeWastewaterCWWF
Federal contribution
$175,322
Federal share50%

of $350.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Loyalist
Construction start
Feb 1, 2017(actual)
Construction end
Nov 3, 2017(actual)

Against the original forecast

  • Construction end16 months earlyforecast Mar 1, 2019

Also in Loyalist

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49140 in the federal list. How to read these figures.