Back to projects

Detailed design and construction - Water main relining on Cambridge Crescent

Loyalist, Ontario

completeDrinking WaterCWWF
Federal contribution
$302,088
Federal share50%

of $604.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Loyalist
Construction start
Dec 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start10 months lateforecast Feb 1, 2017
  • Construction end9 months lateforecast Apr 1, 2018

Also in Loyalist

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49137 in the federal list. How to read these figures.