Water/Wastewater Deficiencies
Federal contribution
$260,274
Federal share31%
of $837.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 22, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Anishinabe of Wauzhushk Onigum
- Construction start
- Aug 15, 2016(actual)
- Construction end
- Mar 31, 2017(actual)
Also in Kenora