Village of Consort Wastewater System Upgrades - Installation of new Forcemain

Consort, Alberta

completeWastewaterSCF
Federal contribution
$532,093
Federal share26%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Consort
Construction start
Nov 1, 2018(actual)
Construction end
Jul 13, 2020(actual)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2019
  • Construction end2 months lateforecast Apr 30, 2020