Village of Consort Wastewater System Upgrades - Installation of new Forcemain
Federal contribution
$532,093
Federal share26%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Consort
- Construction start
- Nov 1, 2018(actual)
- Construction end
- Jul 13, 2020(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2019
- Construction end2 months lateforecast Apr 30, 2020
Also in Consort