Consort Aquatic Facility Upgrades

Consort, Alberta

completeRecreationRNIS
Federal contribution
$622,400
Federal share40%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2020
20212022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Consort
Construction start
Aug 4, 2021(actual)
Construction end
Jul 1, 2022(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 21, 2021
  • Construction end2 weeks earlyforecast Jul 15, 2022