Water Distribution Pumping Station Retrofit
Federal contribution
$321,009
Federal share24%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018202020222024
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Consort
- Construction start
- Apr 14, 2022(actual)
- Construction end
- Nov 10, 2023(actual)
Against the original forecast
- Construction start11 months earlyforecast Mar 1, 2023
- Construction end3 weeks earlyforecast Nov 30, 2023