Back to projects

Village of Consort replacement of Water and Wastewater pipelines along 49 and 52 Avenue

Consort, Alberta

completeDrinking WaterSCF
Federal contribution
$1.4M
$1,447,000
Federal share33%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Consort
Construction start
Jun 1, 2016(actual)
Construction end
Dec 20, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2016
  • Construction end3 weeks lateforecast Nov 30, 2018