Oak Point Drive Water & Sewer Extensions

Killarney-Turtle Mountain, Manitoba

completeDrinking WaterSCF
Federal contribution
$550,000
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Mar 8, 2016(actual)
Construction end
Dec 21, 2016(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 1, 2016
  • Construction end7 weeks lateforecast Oct 31, 2016