Mountain Avenue and Broadway and Mountain Backlane Sewer and Water Replacement - Phase II

Killarney-Turtle Mountain, Manitoba

completeWastewaterGIS
Federal contribution
$507,560
Federal share40%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2022
2023
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 20, 2022(actual)
Construction end
Dec 19, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2022
  • Construction end5 months lateforecast Jul 31, 2022