Broadway and Mountain Backlane Sewer and Water Replacement
Killarney-Turtle Mountain, Manitoba
Federal contribution
$550,000
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2017
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Killarney - Turtle Mountain
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Sep 15, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 4, 2017
- Construction end2 weeks earlyforecast Sep 30, 2017
Also in Killarney-Turtle Mountain
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49294 in the federal list. How to read these figures.