Killarney Turtle Mountain - Handi-Van Purchase

Killarney-Turtle Mountain, Manitoba

completePublic TransitPTIF
Federal contribution
$39,000
Federal share50%

of $78.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 28, 2017(actual)
Construction end
Aug 11, 2017(actual)

Against the original forecast

  • Construction end5 months earlyforecast Dec 31, 2017

Also in Killarney-Turtle Mountain

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49248 in the federal list. How to read these figures.