New Trunk Sewer Phase 2
Federal contribution
$410,199
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Neepawa
- Construction start
- Sep 12, 2016(actual)
- Construction end
- Jan 23, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 11, 2016
- Construction end9 months earlyforecast Oct 31, 2017
Also in Neepawa