Back to projects

New Trunk Sewer Phase 2

Neepawa, Manitoba

completeWastewaterSCF
Federal contribution
$410,199
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Neepawa
Construction start
Sep 12, 2016(actual)
Construction end
Jan 23, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 11, 2016
  • Construction end9 months earlyforecast Oct 31, 2017

Also in Neepawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46339 in the federal list. How to read these figures.