Neepawa Wastewater Treatment System Upgrade and Expansion - Phase II
Federal contribution
$2.3M
$2,283,400
Federal share40%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2022
2023202420252026
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Neepawa
- Construction start
- Feb 6, 2023(actual)
- Construction end
- Nov 30, 2025(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jan 15, 2023
- Construction end4 months earlyforecast Mar 31, 2026
Also in Neepawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62690 in the federal list. How to read these figures.