Wastewater Lagoon Upgrades
Federal contribution
$2.2M
$2,200,000
Federal share50%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2019
201920202021
Built
Approved 11 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Neepawa
- Construction start
- Sep 26, 2018(actual)
- Construction end
- Jan 15, 2021(actual)
Against the original forecast
- Construction end2 weeks lateforecast Dec 31, 2020
Also in Neepawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52151 in the federal list. How to read these figures.