Neepawa Multi-Use Trail Park
Federal contribution
$550,000
Federal share80%
of $687.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 17, 2022
2023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Neepawa
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Sep 1, 2021
- Construction end13 months earlyforecast Dec 31, 2024
Also in Neepawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61520 in the federal list. How to read these figures.