Water and Sewer Upgrades
Conception Bay South, Newfoundland and Labrador
Federal contribution
$793,908
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
201820192020202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Conception Bay South
- Construction start
- Oct 17, 2017(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2017
- Construction end13 months lateforecast Nov 30, 2021