Schedule
Announced and approvedMay 20, 2016
2017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Corner Brook
- Construction start
- May 20, 2016(actual)
- Construction end
- Apr 27, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 31, 2019