Back to projects

Legion Rd Upgrading

Conception Bay South, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$318,584
Federal share12%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
2017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 24, 2018(actual)
Construction end
Sep 4, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2018
  • Construction end5 months lateforecast Mar 31, 2020

Also in Conception Bay South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46689 in the federal list. How to read these figures.