Schedule
Announced and approvedMay 20, 2016
2017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Conception Bay South
- Construction start
- Sep 24, 2018(actual)
- Construction end
- Sep 4, 2020(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 1, 2018
- Construction end5 months lateforecast Mar 31, 2020