Watson Lake Reservoir

Watson Lake, Yukon

completeDrinking WaterCWWF
Federal contribution
$2.2M
$2,205,802
Federal share72%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Watson Lake
Construction start
Jul 17, 2017(actual)
Construction end
Nov 19, 2018(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Aug 1, 2017
  • Construction end12 months earlyforecast Nov 30, 2019