Watson Lake Reservoir
Federal contribution
$2.2M
$2,205,802
Federal share72%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 22, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Nov 19, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Aug 1, 2017
- Construction end12 months earlyforecast Nov 30, 2019