Haines Junction Lagoon upgrades

Haines Junction, Yukon

completeWastewaterCWWF
Federal contribution
$2.3M
$2,347,900
Federal share71%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Haines Junction
Construction start
Sep 1, 2017(actual)
Construction end
Sep 5, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2017
  • Construction end19 months earlyforecast Mar 31, 2021