Watson Lake Wet Well and Lift Station
Federal contribution
$2.1M
$2,145,776
Federal share68%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 22, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Nov 27, 2019(actual)
Against the original forecast
- Construction start9 months earlyforecast May 1, 2018
- Construction end5 weeks earlyforecast Dec 31, 2019
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46924 in the federal list. How to read these figures.