Watson Lake Wet Well and Lift Station

Watson Lake, Yukon

completeWastewaterCWWF
Federal contribution
$2.1M
$2,145,776
Federal share68%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Watson Lake
Construction start
Jul 17, 2017(actual)
Construction end
Nov 27, 2019(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 1, 2018
  • Construction end5 weeks earlyforecast Dec 31, 2019