Dawson Airport Runway Resurfacing
Federal contribution
$201,150
Federal share75%
of $268.2K total eligible cost; the rest comes from other partners.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Dawson
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Sep 28, 2016(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2016
- Construction end4 weeks lateforecast Sep 2, 2016
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46952 in the federal list. How to read these figures.