Dawson Airport Runway Resurfacing

Dawson City, Yukon

completeRegional And Local AirportsSCF
Federal contribution
$201,150
Federal share75%

of $268.2K total eligible cost; the rest comes from other partners.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Dawson
Construction start
Sep 1, 2016(actual)
Construction end
Sep 28, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2016
  • Construction end4 weeks lateforecast Sep 2, 2016

Also in Dawson City

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46952 in the federal list. How to read these figures.