Lincoln Road Water and Sewer Replacement
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$770,810
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 7, 2016
ApprovedJun 29, 2017
201720182019
Built
Approved 12 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Grand Falls-Windsor
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2017
- Construction end6 months lateforecast Dec 31, 2018
Also in Grand Falls-Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47090 in the federal list. How to read these figures.