Three Bear Mountain Trail
Corner Brook, Newfoundland and Labrador
Federal contribution
$69,209
Federal share38%
of $181.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Corner Brook
- Construction start
- Sep 23, 2019(actual)
- Construction end
- Feb 4, 2020(actual)
Against the original forecast
- Construction end2 months lateforecast Nov 30, 2019
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47098 in the federal list. How to read these figures.