Water Main Reliability
Federal contribution
$594,620
Federal share46%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Oct 16, 2017(actual)
- Construction end
- Jul 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 28, 2017
- Construction end4 weeks lateforecast Jun 30, 2018
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47140 in the federal list. How to read these figures.