Back to projects

Pond Street Lift Station

Cornwall, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$619,092
Federal share49%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Cornwall
Construction start
Jun 19, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction end12 months lateforecast Sep 30, 2017

Also in Cornwall