Storm and sanitary sewer separation project on Brook Street

Lunenburg, Nova Scotia

completeWastewaterCWWF
Federal contribution
$1.1M
$1,106,561
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lunenburg
Construction start
May 1, 2017(actual)
Construction end
Aug 28, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2017
  • Construction end17 months lateforecast Mar 31, 2019