Back to projects

Installation of air diffusers in two distribution reservoirs

New Minas, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$47,072
Federal share42%

of $112.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of New Minas
Construction start
Dec 12, 2017(actual)
Construction end
Dec 21, 2018(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2019

Also in New Minas