Industrial park, phase 2 Aviation Avenue services extension
Federal contribution
$1.2M
$1,215,271
Federal share50%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Dieppe
- Construction start
- Nov 21, 2016(actual)
- Construction end
- Dec 20, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 19, 2016
- Construction end9 months lateforecast Mar 31, 2019
Also in Dieppe