Sewer Separation and Upgrades Along Acadie Avenue, Virginia Avenue, and Ste-Croix Street
Federal contribution
$257,064
Federal share50%
of $514.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Dieppe
- Construction start
- May 29, 2017(actual)
- Construction end
- Nov 1, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
Also in Dieppe
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47300 in the federal list. How to read these figures.