Sewer Separation and Upgrades Along Acadie Avenue, Virginia Avenue, and Ste-Croix Street

Dieppe, New Brunswick

completeWastewaterCWWF
Federal contribution
$257,064
Federal share50%

of $514.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Dieppe
Construction start
May 29, 2017(actual)
Construction end
Nov 1, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017