Watermain and Storm Sewer Renewal on Various Streets

Riverview, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$1.1M
$1,132,645
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Riverview
Construction start
May 1, 2017(actual)
Construction end
Jul 27, 2018(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 15, 2017
  • Construction end10 months lateforecast Sep 15, 2017

Also in Riverview

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47329 in the federal list. How to read these figures.