Watermain and Storm Sewer Renewal on Various Streets
Federal contribution
$1.1M
$1,132,645
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Riverview
- Construction start
- May 1, 2017(actual)
- Construction end
- Jul 27, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 15, 2017
- Construction end10 months lateforecast Sep 15, 2017
Also in Riverview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47329 in the federal list. How to read these figures.