Back to projects

New Sewage Pumping Station and Piping - End of City Line at Fort Dufferin Road

Saint John, New Brunswick

completeWastewaterCWWF
Federal contribution
$136,024
Federal share50%

of $272.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Jul 10, 2017(actual)
Construction end
Jan 8, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 26, 2017
  • Construction end11 months earlyforecast Nov 30, 2018

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47332 in the federal list. How to read these figures.