Hespeler Wastewater Treatment Plant Upgrades

Cambridge, Ontario

completeWastewaterCWWF
Federal contribution
$2.0M
$2,000,000
Federal share50%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2016(actual)
Construction end
Dec 20, 2018(actual)

Against the original forecast

  • Construction end6 months lateforecast Jun 30, 2018

Also in Cambridge