Hespeler Wastewater Treatment Plant Upgrades
Federal contribution
$2.0M
$2,000,000
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 14, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Jul 1, 2016(actual)
- Construction end
- Dec 20, 2018(actual)
Against the original forecast
- Construction end6 months lateforecast Jun 30, 2018
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47535 in the federal list. How to read these figures.