Community Wastewater System Improvements
Federal contribution
$375,000
Federal share50%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Golden
- Construction start
- Aug 8, 2017(actual)
- Construction end
- Nov 16, 2017(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 5, 2017
- Construction end2 weeks earlyforecast Nov 30, 2017
Also in Golden
- Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge$215.2M
- Kicking Horse Canyon Highway Improvement Project - Phase 2$62.5M
- Trans-Canada Highway 1 - Quartz Creek$49.9M
- Highway 1 Selkirk Mountain Four-Laning$31.5M
- TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE$28.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47681 in the federal list. How to read these figures.