Back to projects

Community Wastewater System Improvements

Golden, British Columbia

completeWastewaterCWWF
Federal contribution
$375,000
Federal share50%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Golden
Construction start
Aug 8, 2017(actual)
Construction end
Nov 16, 2017(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Sep 5, 2017
  • Construction end2 weeks earlyforecast Nov 30, 2017

Also in Golden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47681 in the federal list. How to read these figures.