Repairs to tennis courts in Donnacona
Federal contribution
$92,389
Federal share33%
of $277.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2017
20172018201920202021
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Donnacona
- Construction start
- Nov 22, 2016(actual)
- Construction end
- Dec 15, 2020(actual)
Against the original forecast
- Construction start5 months earlyforecast May 2, 2017
- Construction end3.5 years lateforecast Jun 23, 2017
Also in Donnacona
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47741 in the federal list. How to read these figures.