Renewal of water pipes

Donnacona, Quebec

completeDrinking WaterCWWF
Federal contribution
$2.5M
$2,487,714
Federal share48%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Donnacona
Construction start
Jun 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2017
  • Construction end4 weeks earlyforecast Apr 30, 2018

Also in Donnacona

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49042 in the federal list. How to read these figures.