Set up a unit for a clientele presenting psychological and behavioral symptoms of dementia (BPSD) and renovate some of the obsolescence of the asset maintenance master plan
Federal contribution
$580,800
Federal share80%
of $726.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Capitale-Nationale
- Construction start
- Nov 1, 2021(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2021
- Construction end12 months lateforecast Aug 31, 2022
Also in Donnacona
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59048 in the federal list. How to read these figures.