Set up a unit for a clientele presenting psychological and behavioral symptoms of dementia (BPSD) and renovate some of the obsolescence of the asset maintenance master plan

Donnacona, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$580,800
Federal share80%

of $726.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2021
  • Construction end12 months lateforecast Aug 31, 2022