Water Systems Upgrades
Federal contribution
$600,140
Federal share40%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Donnacona
- Construction start
- May 3, 2021(actual)
- Construction end
- Oct 29, 2021(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Nov 30, 2021
Also in Donnacona
- Renewal of water pipes$2.5M
- Construction of an aquatic center$1.8M
- Donnacona Drinking Water Plant$1.2M
- Access Ramp for Highway 40 and 2nd Rural Route$973.0K
- Set up a unit for a clientele presenting psychological and behavioral symptoms of dementia (BPSD) and renovate some of the obsolescence of the asset maintenance master plan$580.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56304 in the federal list. How to read these figures.