Construction of an aquatic center
Federal contribution
$1.8M
$1,833,333
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2017
2018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Donnacona
- Construction start
- Apr 20, 2017(actual)
- Construction end
- Jul 21, 2021(actual)
Against the original forecast
- Construction start2.4 years earlyforecast Sep 16, 2019
- Construction end4 months lateforecast Mar 31, 2021
Also in Donnacona
- Renewal of water pipes$2.5M
- Donnacona Drinking Water Plant$1.2M
- Access Ramp for Highway 40 and 2nd Rural Route$973.0K
- Water Systems Upgrades$600.1K
- Set up a unit for a clientele presenting psychological and behavioral symptoms of dementia (BPSD) and renovate some of the obsolescence of the asset maintenance master plan$580.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49990 in the federal list. How to read these figures.